One Stop Solution Manufacturer for all kind of Stamping Products and CNC lathed products.
How to maintain the chip removal machine at ordinary times. While we are using the chip conveyor, the equipment is running every day. We should also set up a maintenance plan for the chip conveyor in time to ensure the normal operation of the equipment.
Mechanical Transmission
1. The dimensional accuracy, roughness, center distance, shape and position tolerance of each shaft hole of the casing shall meet the requirements of technical documents.
2. The threaded holes, positioning holes and table on the casing and the connecting cover shall meet the requirements of the technical documents after being repaired.
3. The bearing has no obvious signs of wear, and the clearance meets the requirements.
4. The fastener has no obvious plastic deformation. (Guide: Is there a difference between a kind of welding nail and a pressure riveting screw)
5. There is no damage to the parts, no obvious signs of wear and deformation.
6. The seals and organic hoses are all updated.
7. When assembling, all parts must be carefully cleaned, there must be no rust spots, and there must be no dirt in the casing.
8. After installation and adjustment of each transmission part, it meets the requirements of technical documents.
9. The reducer is filled with lubricating oil as required. The hydraulic coupling is subjected to a pressure test and injected with a specified variety and volume of media.
10. The dynamic balance test of brake disc, coupling and coupler meets the requirements of technical documents.
11. There is no leakage of reducer and sprocket assembly. The cooling and lubricating devices are complete and intact, without leakage.
More related press machine industry news:
Contact Person: Steven Yan
Whatsapp: +86 15916928704
Wechat: CITY-STOP
Phone: +0086 159 1692 8704
E-MAIL: ym@syjwj.com.cn
One-stop manufacturer for all kind of stamping products and CNC lathed products.